Pre-Filing Milestone

Proposed Date

FERC Regulation

Responsible Party

NOI/PAD and Request to Utilize the ILP

August 2, 2023

5.3(d)(2)

IFP

Initiate Tribal Consultation

August 17, 2023

5.7

FERC

Issue Notice of Commencement of Proceeding and SD1

October 1, 2023

5.8(a)(c)

FERC

Scoping Meetings and Projects Site Visit

October 25 & 26, 2023

5.8(b)(viii)

FERC

File Comments on PAD/SD1 and Study Requests

November 30, 2023

5.9(a)(b)

Stakeholders

Issue SD2 (if necessary)

January 14, 2024

5.10

FERC

File Proposed Study Plan (PSP)

January 14, 2024

5.11(a)

IFP

Proposed Study Plan (PSP) Meeting

February 13, 2024

5.11(e)

IFP

File Comments on Proposed Study Plan

April 13, 2024

5.12

Stakeholders

File Revised Study Plan (RSP)

May 13, 2024

5.13(a)

IFP

Comments on RSP

May 28, 2024

5.13(b)

 

Issue Director’s Study Plan Determination

June 12, 2024

5.13(c)

FERC

File Any Study Disputes

July 2, 2024

5.14(a)

Mandatory Conditioning Agencies

Select Third Dispute Resolution Panel Member

July 17, 2024

5.14(d)

Dispute Panel

Convene Dispute Resolution Panel

July 22, 2024

5.14(d)(3)

Dispute Panel

File Comments on Study Disputes

July 27, 2024

5.14(i)

Dispute Panel

Dispute Resolution Panel Technical Conference

August 1, 2024

5.14(j)

Dispute Panel

Issue Dispute Resolution Panel Findings

August 21, 2024

5.14(k)

Dispute Panel

Issue Director’s Study Dispute Determination

September 10, 2024

5.14(l)

FERC

First Study Season

Summer 2024

5.15(a)

IFP

File Initial Study Report (ISR)

June 12, 2025

5.15(c)(1)

IFP

Initial Study Report Meeting

June 27, 2025

5.15(c)(2)

Stakeholders

File Initial Study Report Meeting Summary

July 12, 2025

5.15(c)(3)

IFP

File Disagreements/Requests to Amend Study Plan

August 11, 2025

5.15(c)(4)

Stakeholders

File Responses to Disagreements/Amendments

September 10, 2025

5.15(c)(5)

Stakeholders

Issue Director’s Determination on Disagreements/Amendments

October 10, 2025

5.15(c)(6)

FERC

Second Study Season (if needed)

Spring/Summer 2025

5.15(a)

IFP

File Updated Study Report (USR)

June 12, 2026

5.15(c)(1)

IFP

Updated Study Report (USR) Meeting

June 27, 2026

5.15(c)(2)

Stakeholders

File Updated Study Report Meeting Summary

July 12, 2026

5.15(c)(3)

IFP

File Disagreements/Requests to Amend Study Plan

August 11, 2026

5.15(f)

Stakeholders

File Responses to Disagreements/Amendments

September 10, 2026

5.15(f)

Stakeholders

Issue Director’s Determination on Disagreements/Amendments

October 10, 2026

5.15(f)

FERC

File Preliminary Licensing Proposal (or Draft License Application)

September 3, 2026

5.16(a)-(c)

IFP

File comments on Preliminary Licensing Proposal (or Draft License Application)

December 2, 2026

5.16(e)

Stakeholders

File Final License Application

January 31, 2027

5.17

IFP

Issue Public Notice of Final License Application Filing

February 14, 2027

5.17(d)(2)

FERC

 


The ILP process is outlined below. Additional information regarding the ILP process is available on the FERC website here.

chart